How to find a contractor for building works
Contents |
[edit] Introduction
Contractors are organisations appointed by clients (or employers) to carry out construction works. This role is vital to the success of a project, and so great care should be taken to ensure an appropriate contractor is selected. This may involve seeking advice from consultants if the client is inexperienced.
In the construction industry, the process of selecting a contractor is generally referred to as ‘tendering’ and involves preparing tender documents that describe the project, and then inviting tender submissions from prospective contractors from which as selection can be made.
This article describes the process commonly used to put together a list of prospective contractors. Other processes may be used on certain types of projects, such as Private Finance Initiative (PFI) projects.
- For information about selecting a contractor from a list of potential contractors see: How to select a contractor.
- For information about appointing a contractor see: How to appoint a contractor.
[edit] Procurement route
It is first necessary to decide what functions the contractor will be undertaking. The contractual role undertaken by a contractor is referred to as the ‘procurement route’ and will depend on the nature of the work required:
- Its scale and complexity.
- Whether it involves specialist skills or knowledge.
- Its location.
- Whether it involves any design by the contractor.
- Whether it requires early involvement of the contractor to advise on the design.
Most projects are procured following a traditional route, that is, the building is designed in full, then a contractor is appointed to construct the building. However, there are many other different procurement routes available:
- Design and build: A contractor is appointed to design the building (or complete the design) and then to construct it.
- Construction management: A construction manager is appointed to contract and manage individual trades on behalf of the client.
- Management contractor: A management contractor is appointed to contract individual trades directly.
For more information, see Procurement route.
[edit] Tender documents
Once the procurement route has been selected, it is then necessary to prepare a description of what precisely the contractor will be expected to do, so that appropriate contractors can be identified and prices obtained.
This may involve preparing:
- Design drawings.
- Specifications.
- Pricing documents.
- A contract.
- Selection criteria.
This will involve considering issues such as:
- Whether the contractor will be the principal contractor with responsibilities under the CDM regulations.
- Whether building information modelling (BIM) will be used.
- Who the contract administrator will be.
- Start and finish dates.
- The contract that will be used.
- The contract conditions that will be applied.
For more information, see Tender documentation and Construction contract.
[edit] Identifying potential contractors
For some straight-forward projects there may be many contractors that could undertake the contract, whereas for some complex specialist works there may be very few.
Typically, clients will wish to identify a number of potential contractors, then perhaps reduce this down to a shortlist of 3 or 4 from whom to ask for prices. Negotiations may then be entered into with the preferred contractor, and an appointment made.
It may be possible to put together a list of potential contractors based on:
- Existing relationships, such as a contractor the client has worked with before, or a framework agreement.
- Recommendations from other clients or from consultants such as an architect, quantity surveyor or project manager.
- Researching contractors that have carried out similar work in the past.
- Advertising. Historically, advertising was only appropriate for larger projects, however, specialist sites now exist that can allow clients to advertise small jobs and to see reviews of respondents before inviting tenders or making a selection. Large projects that involve public funding may be required to advertise in the official journal of the EU (OJEU), and this can be a time consuming process.
- Competition. Generally this is only appropriate if the project involves design. Competitions can be open, or by invitation. If the project has not been designed, or fully designed, it is possible that it will not have planning permission yet. In this case it is important to establish who is responsible for obtaining permission.
On complex specialist projects, it may be difficult to obtain any prices, particularly if the site is remote, or the industry is busy. In this case, it may be necessary to change the scope or nature of the works. If only one price can be obtained, it may be wise to seek professional advice about whether the price and tender are reasonable, or whether the works should be re-tendered, perhaps with changes to make sure more responses are received, or taking more active steps to ensure contractors respond.
The next stage is the process of selecting a preferred contractor from the list of potential contractors. To find out more, see How to select a contractor.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings for people to come home to... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”